Svenska kraftnät: Ringhals 3 yearly maintenance -- SE2 → SE3
What the source reported
Source-reportedNord Pool UMM: Svenska kraftnät reports Ringhals 3 yearly maintenance for SE2 → SE3. Unavailable 2000 mw of 7700 mw from 2026-05-03 22:00:00 to 2026-11-07 22:00:00. Remarks: Updated end time. The capacities depend on availability of remedial actions, ambient temperatures and expected load flow conditions The Nordic TSOs acknowledge that our current tool for estimating the.
- Publication
- Nord Pool Urgent Market Messages (UMM) · Stock Exchange/Regulatory Announcements
- Published
- 20th October 2026
- Original report
- umm.nordpoolgroup.com
ProcIntel stores what the source published in its feed — a headline, a summary and a link. It does not store or reproduce the full article.
What ProcIntel recorded
ProcIntel-derived- Category
- Supplier & Corporate Risk
- Geography
- Norway
- Organisations
- None identified
- Collected
- 20th October 2026 · 12:02
Initial assessment ProcIntel's automatic, provisional read of this individual Signal -- Initial Significance and Initial Confidence, computed deterministically before any Event extraction or human review.
A provisional, automatically computed reading of this individual Signal, before Event extraction or human review. Not a final rating.
Initial Significance Low (14.0/100). Strongest contributor: Procurement Impact (6.0/30 points). Limiting factor: Geographic Breadth (0.0/10 points). Initial Confidence Moderate (51.5/100, data sufficiency: Partial). Strongest contributor: Source Authority (40.0/40 points). Limiting factor: Corroboration (2.5/25 points).
- Strongest contributor
- Procurement Impact
- Limiting factor
- Geographic Breadth